Main Street Construction Resumes

To help the businesses of downtown G&L is looking at opening the street back up on weekends (Fri-Sun).  They would like to get through the first week and see how things are going, but re-opening for the weekends is their intent.

Their plan for construction is to perform demolition on one side of the street, while the underground work (root barrier, electric, broadband, underdrain) proceed with demolition on the other side of the street then flip the underground crew across the street while the first crew preps for sidewalk.  The first week work may be limited to one side of the street but after that they will be working on both.